Partnership recorded as #9601090553 and the First Amendment to said Agreement recorded as #9707291427, and the Northridge Urban Planned Development and Fully Contained Community Development Agreement between King County and the Quadrant Corporation recorded as #9702181008.
Monitoring initiation and duration of specified parameters is often linked to 75 percent subbasin buildout. At the end of the 2010 water year, eight out of nine UPD subbasins had reached this threshold; the exception was the Big Bear Creek (BBC) subbasin, at only 25 percent buildout.
The Trilogy and Redmond Ridge monitoring plans identified specific threshold exceedance criteria to evaluate the effectiveness of protective actions. Exceedance of one or more thresholds would trigger an investigation into the cause of the exceedance and required: (1) corrective action to mitigate project-related impacts, should the exceedances be attributable to UPD development, or (2) reconsideration of the threshold. Each threshold criterion is evaluated in this report, and recommendations are provided when exceedances are identified. Through the 2010 water year, no corrective actions are recommended.
Outside of a few examples of threshold exceedances that are documented in this report but could not conclusively be linked to UPD development, measurable negative impacts to monitored receiving streams or on-site wetlands have not been demonstrated during the 12-year UPD monitoring program. These results suggest that the 200-ft buffer averaging of buffers around streams and wetlands in addition to stormwater facilities (including retention ponds, infiltration ponds, conveyance systems, and water quality treatments) appear to have effectively mitigated the project impacts to the extent they can be measured at this time. No remediation of the constructed facilities is required at this time and the monitoring funds set aside for that purpose have been returned to the developer. In summary, the UPD monitoring demonstrates to the extent possible that the management actions required for both Redmond Ridge and Trilogy appear to have provided the environmental protections intended for these UPDs. This report is the final monitoring report and concludes WLRD's monitoring obligations for the Redmond Ridge and Trilogy UPDs.
In individual subsections, the monitoring procedures and results from the different elements of the 2008-10 monitoring period are summarized for all representative monitoring objectives.